§ 8.04.130. Registration fees.  


Latest version.
  • The control board shall, by regulation, classify all articles, machines, and equipment and set the initial and renewal registration fees therefor; but, such registration fees shall not exceed those indicated in the following schedule:

    A.

    Fuel burning equipment for producing indirect heat other than those used in one- and two-family residences:

    1.

    Nongas fired equipment with a maximum fuel input less than four million BTU per hour ..... $10.00

    2.

    Nongas fired equipment, and gas fired equipment having provision to burn oil or solid fuels, with a maximum input over four million BTU per hour and less than twenty million BTU per hour ..... $25.00

    3.

    Same as subsection (A)(2) of this section, but with a maximum fuel input over twenty million BTU per hour and less than two hundred million BTU per hour ..... $50.00

    4.

    Same as subsection (A)(2) of this section, but with a maximum fuel input over two hundred million BTU per hour ..... $100.00

    B.

    Incinerators ..... $10.00 each

    C.

    Asphalt batching plants ..... $100.00 each

    D.

    Sand, rock, and gravel plants ..... $50.00 each

    E.

    1.

    Chemical process units with less than ten employees at the plant site, for each process ..... $25.00

    2.

    Chemical process units with ten or more employees at the plant site, for each process ..... $200.00

    F.

    1.

    Metal melting and reclaiming process with less than ten employees at the plant site, for each process$25.00

    2.

    Metal melting and reclaiming processes with ten or more employees at the plant site, for each process ..... $200.00

    G.

    Inedible animal byproduct processing ..... $50.00

    H.

    Lime and gypsum process, for each process ..... $200.00

    (except when processed at mine sites located outside the boundaries of the Las Vegas valley water district, in which case, the registration fee shall be for each process) $50.00

    I.

    Plants, or operations apart from plants, handling or transferring dust producing materials not elsewhere classified herein ..... $25.00

    J.

    The maximum registration fee for all operations of any one company at an individual plant site shall not exceed ..... $500.00

(Prior code § 7.35.130)